| Perkins Court - Harvard College Observatory Cambridge, MA
Project Size 6,000 s.f. Plaza Deck Reconstruction
Project Background The project entailed the removal of
the existing plaza deck pavers, and overburden, as well as the
installation of a new waterproofing membrane and new plaza deck pavers.
Project Description The plaza deck at the Astrophysics
Department facility at Harvard College is also a courtyard for the
science building. It has very difficult access which proved to be a
challenge that was solved by Metropolitan prior to project commencement. The
existing plaza deck membrane system was located under concrete pavers.
The reconstruction project
necessitated removing the over-burden, consisting of 2' X 2' concrete
pavers and 12" of drainage fill. Since the logistics and access were
difficult, a system had to be devised and implemented so as to handle
the material removal efficiently. Metropolitan
devised a conveyor system which was set up on a single access stairway
which served as the means in which the pavers were taken down from the
deck. In addition, the entire construction project was handled in a
manner that would not cause disruption to science offices adjacent to
the plaza deck.
A laser laboratory is located/housed under the plaza deck, and
encased in a 2 foot thick reinforced steel concrete vault. One of the
technical problems in constructing the new plaza deck was the manner in
which membrane tied into the cavity walls adjacent to the plaza deck.
The new membrane had to be tied into the wall waterproofing system so as
to effectively
seal the building envelope. The
first two courses of masonry had to be removed from the adjacent cavity
wall to allow access to properly tie the new membrane/waterproofing
system into the underlying back-up wall waterproofing. The remaining
brick courses of the forty foot high wall needed to be properly braced
during this tedious operation.
A high tech, reinforced PVC membrane was utilized. Metropolitan
employed a heat-fusing technique in the installation process, thus
achieving a monolithic membrane assembly. As a result of the
heat-fusing, the seams of the membrane are even stronger than the
membrane itself. Consequently, the seams will not be adversely affected
by continuous water submersion, as water penetrates the overburden which
consists of new drainage fill and new pavers. Metropolitan's
installation of the new
membrane for the project was a loose laid membrane that included a
containment grid system so as to ensure that any water infiltration
problem that may occur in the future will be confined within a grid,
making it much easier to pinpoint its origin. Prior to installing the
overburden, the entire plaza deck, including each grid system, was
flood-tested with a dye, to assure that the deck was completely
waterproof.
In addition to the difficult access, throughout the project
Metropolitan had to work around and keep protected a valuable and
irreplaceable sculpture which is permanently affixed to the plaza deck
courtyard.
|