| Willard Building Quincy, MA
Project Size 3-story historic structure requiring extensive restoration of masonry gables, roofs, copper gutters, and chimney
Project Background
A
turn-of-the-century school building, the Willard Building had been
converted to office space. The building required exterior waterproofing
and complicated restoration work. Remedial repair measures had
previously been taken during the conversion but were unsuccessful in
solving the water infiltration and actually accelerated the
deterioration of the masonry structure.
Project Description Water damage had caused
considerable structural deterioration to the building's 10 gables. The
structural damage to the gables' parapets extended 18 inches below the
roof
line. The
granite coping stones which capped the parapets weighed an average of
500 lbs. As a result of the deterioration, stones were subject to fall
off the building, as the brick masonry beneath also had significant
deterioration. Metropolitan was contracted to handle the entire
restoration project.
Since
the coping stones were keyed in to the parapet, it was necessary for
Metropolitan to devise an innovative way to take the granite coping
stones off the parapet while keeping the structural wall intact. Using a
40 ton crane and a specially devised clamping apparatus, Metropolitan
was able to keep the wall intact during what was a very delicate
operation. Stones had to then be reconstructed on the gables after
rebuilding the deteriorated masonry parapets. All mortar for the
project was color-matched to existing building mortar.
Upon completion of the structural work and reconstruction, a
phased construction of the roof was undertaken. The project features
the installation of an entirely new roofing system with an intricately
designed copper gutter system. The copper gutters, which featured OGEE
profiles, were fabricated and reinstalled. Metropolitan is now in the
final phase of
installation of the new composite shingle roofing system for the
historic building. The complex and intricate roof layout features
numerous dormers, skylights and levels, adding to the complexity of the
roofing project. In conjunction with the fabrication and installation
of copper gutters, Metropolitan has installed an ice barrier at the
eaves of the new roof. An
ice and water shield membrane (a relatively new roofing material)
self-adheres and seals to the roof sheathing at the eaves. The membrane,
which is concealed under the new roofing, is specially designed to
prevent water from backing up into the building as a result of ice
damming.
The Willard Building has remained occupied during the entire
reconstruction process, and Metropolitan has handled the entire
restoration project in a manner so as to not disrupt the building's high
profile tenants.
Special Project Features: Lime-based Mortar Batched On-Site To Match Original Mortar Metropolitan
took special measures in mortar-matching to the original mortar of the
historic structure. The Willard Building, like most historic brick
structures built in that era, was constructed using lime-based mortar,
which is soft, waterproof, and flexible (consisting of no Portland
cement). Lime-based mortar is compatible with the brick of that era
which was not as hard as current day brick. Lime mortar is flexible in
nature. It's properties, in fact, allow it to move, breathe, and repair
itself, as water works with the mortar to reactivate the lime.
Metropolitan matched the building's mortar for compressive
strength, porosity, and so as to be compatible with the porosity of the
brick. Mortar was batched on-site and consisted of a high lime content
mix with color added. Consistent batching techniques were employed
throughout the project.
|